D44H0129 - F0006 Update dates based on homebuilder processes
Parameter Name | Data Item | Data Type | Req/Opt | I/O/Both |
---|---|---|---|---|
cProgrammerMode_EV01 | EV01 | char | REQ | INPUT |
An option that specifies the type of processing for an event. | ||||
szCostCenter_MCU | MCU | char | REQ | INPUT |
An alphanumeric code that identifies a separate entity within a business for which you want to track costs. For example, a business unit
| ||||
jdActualStartDate_D2J | D2J | JDEDATE | OPT | NONE |
Enter the actual start date for a project or job in this field. Use this information for reporting purposes. | ||||
jdActualCompletion_D4J | D4J | JDEDATE | OPT | NONE |
Enter the actual completion date for a project or job in this field. Use this information for reporting purposes. | ||||
jdEscrowCloseDate_D5J | D5J | JDEDATE | OPT | NONE |
Enter a date that relates to a project or job in this field. Use the information for reporting purposes. This date is user defined. | ||||
cErrorFlag_EV01 | EV01 | char | OPT | OUTPUT |
An option that specifies the type of processing for an event. | ||||
szProgramId_PID | PID | char | REQ | INPUT |
The number that identifies the batch or interactive program (batch or interactive object). For example, the number of the Sales Order Entry
|
None |
None |