Function will take date passed to it add passed number of days to the date . It will then check the
resulting date to see what day of the week it is. If it is Saturday or Sunday the function will
increase the date to Monday . The resulting date will then be passed back
^
D0200003 - Calculate Next Weekday
Parameter Name | Data Item | Data Type | Req/Opt | I/O/Both |
---|---|---|---|---|
jdDateStatusChanged | DCG | JDEDATE | NONE | NONE |
The date the status last changed. | ||||
mnDaysUserDefined | DYUD | MATH_NUMERIC | NONE | NONE |
The days associated with the code defined for this supplemental data type. For example, engineering change order leadtime days
|
None |
None |